Bhadla Solar park Phase IV
The phase IV of Bhadla solar park was developed by Adani. SECI auctioned 250 MW capacity on 9 May 2017.
| Solar park | Bhadla Solar park Phase IV |
|---|---|
| Name of the SPPD | Adani |
| Location | Bhadla, Rajasthan |
| Total capacity installed | 250 MW |
| Date of operation | May 09, 2017 |
| SPD/IPP(s) | 2 (Phelan Energy Group and Avaada Power; SBG Cleantech, Airtel and Foxconn) |
| Tariff(s) in INR | 2.62 (150 MW). 2.63 (100 MW) |
| Total being generated in MW | 28 |
| Total being generated in MWh | 3.336e+4 |
| Total being generated in MVAr | 13 |
| Total Generated in MW | View graph |
| System Voltage Profile | View graph |
| System Frequency | View graph |